Worked example
A 12 × 10 ft patio with 4 × 8 in pavers (the size you enter includes the joint), 5% for cuts, 4 in of compacted base that extends 6 in past the paving on every side, +30% loose material for compaction, 1 in bedding sand, plastic edging in 8 ft pieces with a spike every 1.5 ft, and polymeric joint sand.
- Paved area: 12 × 10 = 120 sq ft; perimeter 44 ft
- Pavers: one paver covers 4 × 8 = 32 sq in = 0.2222 sq ft. 120 × 1.05 ÷ 0.2222 = 567 pavers
- Base footprint: the base is wider than the paving. 120 sq ft + 44 ft × 0.5 ft overrun + 4 corners × 0.5² = 143 sq ft
- Base: 143 × 4/12 = 47.7 cu ft compacted × 1.05 waste = 50.1 cu ft ÷ 27 × 1.86 = 3.45 US tons of crusher run. The loose volume to spread is × 1.30 more: 65.1 cu ft = 2.41 cu yd.
- Sand: 120 × 1/12 = 10 cu ft × 1.10 = 11 cu ft (0.61 tons, or 22 × 0.5 cu ft bags)
- Edging: 44 ft ÷ 8 ft = 5.5 → 6 pieces; spikes: 44 ÷ 1.5 = 30 + 6 (one extra per piece end) = 36
- Joint sand: 120 sq ft ÷ 75 sq ft per bag (a placeholder; use the label of your product) → 2 bags
Why full precision matters: one well-known worked example rounds a 4 × 8 in paver to 0.23 sq ft and gets 2,609 pavers for 600 sq ft. At full precision it is 600 ÷ 0.2222 = 2,700 — 91 more before any cut allowance.
Base and bedding guidance
| Layer | Guidance |
|---|---|
| Compacted aggregate base, patios and walks | at least 4 in (100 mm) over well-drained soil5 |
| Residential driveways | at least 6 in (150 mm)5 |
| Cold climates, wet or weak soils | 2–4 in (50–100 mm) thicker5 |
| Bedding sand | washed concrete sand screeded to a nominal 1 in (25 mm), uncompacted — not stone dust or masonry sand5 |
The base thickness is a design choice that depends on soil, drainage, climate and traffic. The calculator turns your chosen thickness into an order; it doesn’t choose it for you.
Assumptions
- Paver count = area × (1 + cut allowance) ÷ (paver length + joint) × (paver width + joint). If you enter the maker’s coverage per pack or pallet, that is used instead.
- Cut allowance: 5% default for straight layouts; use 10–15% for herringbone, diagonal or curved edges.
- Base: footprint × thickness. The footprint is the paved area plus an overrun on every side (6 in by default; ICPI and manufacturers recommend the base extend beyond the pavers; confirm for your product and soil). Set the overrun to 0 where the base stops at a wall, or enter a footprint override. Weight uses the compacted density (crusher run preset 1.86 tons per cu yd3) and compaction only increases the loose yards.
- Bedding sand: area × thickness × (1 + waste), counted as loose (it is screeded, not compacted); concrete sand preset 1.49 tons per cu yd.
- Joint sand: area ÷ coverage per bag. The default is a placeholder: coverage varies a lot with joint width, paver size and product, so enter the label figure. Add a little extra if you will sweep and re-sweep.
- Geotextile fabric (optional): base footprint + 10% for overlaps, rolled up from your roll size.
- Edging follows the outer perimeter of every area you add. Edges against a house or shared between areas don’t need edging — use the override.
- Not included: border courses in a second paver size, and anything under the base (excavation, soil removal).